SYRIA - THIRD PARTY MONITORING - TOR (SRH05845) Syria
About the mission
Bellow informations are only a summary of the ToR, please find attached all information regarding this Third-Party Monitoring Consultancy.
SI has been working in Syria since 2012, and is today operating in North East Syria (NES) and North West Syria (NWS)
The NES programs provide an integrated assistance in the WASH, NFI, Shelter, FSL sectors to displaced populations and host communities affected by the conflict.
The NWS programs provide WASH and NFI/Winterization support to affected populations.
PRESENTATION OF THE AREA OF INTERVENTION
SI is implementing this project with its national partner IHSAN in continuation of several phases of multi-sectorial responses to basic needs in the Northwest of Syria (NWS). The proposed action applies a basic needs approach, by combining an integrated response package of Water, Sanitation, and Hygiene (WaSH) to IDPs and vulnerable members of host communities in A'zaz District, Jarablus District, Al Bab District. Idleb District, Maaret Tamsrin in Aleppo and Idleb Governorates
OBJECTIVES OF THE CONSULTANCY
The TPM’s main objective is to verify project outputs in both partners’ areas of intervention and ensure that implementation on the ground corresponds to implementation plan, strategy and technical specifications outlined in the project proposal.
Specifically, the TPM will be responsible for:
- Direct observation and verification of implementation and implementation process at site;
- Monitoring and verification of SI and IHSAN activities in locations where SI and IHSAN have limited or no access;
- Provide objective evidence of works in the field, according to SI and IHSAN response strategy and activities planning;
- Evaluate the processes and procedures in place to capture and address community concerns and inquiries, including complaints and feedback mechanism;
- Determine whether the project addresses key needs as perceived by the community and local authorities;
- Provide objective evidence of works in the field, according to SI and IHSAN response strategy and activities planning;
- Situational analysis, identification of implementation and monitoring related challenges and providing recommendations to improve quality.
The proposed TPM focuses on the end stage of the project, in anticipation of the continuation of the response through another grant. The expected TPM services are not planned to be a continuous service spanning across a full project implementation period.
TPM DESIGN AND METHODOLOGY
The consultants or consulting firms interested to support SI and IHSAN on implementing Third Party Monitoring for the project are required to present a detailed TPM proposal including understanding of the TPM scope of work, proposed methodologies to respond to TPM objectives and a detailed plan for data collection plan in the field.
PROPOSED TPM QUESTIONS
The TPM will be requested to monitor the following activities, with a specific focus on water supply and sanitation sub-sectors: