Plant Status Coordination Team Officer (11/08/2022) Eurajoki, Finland
Salary: | GBP1000 - GBP2000 per month + TBC |
Scope (including main skills):
- Plant Status Management Strong PTW Officer as PTW work planner for Blockings, Work
- Orders and Tests
General and technical background expected:
- Mechanical or Electrical engineer
Skills required:
- Engineering degree
- Experience in nuclear power plants Operation
- Deep knowledge on the EPR technology preferred in OL3
- Experience with work planning in MS Project or better in Primavera
- Experience with work orders and blockings.
- Experience with work planning for industrial installations
- Experience with plant management systems
- Ability to work on the different process diagram, isometrics, preparation of solution and support for inventories in the field
- General understanding of mechanics, thermodynamics, fluid mechanics and measurement/instrumentation technology
- General understanding in electrical technology
- Computer literacy in MS-Office
Desired:
- Ability to use the different project data bases, software etc.
Required consent as foreseen:
- To work in controlled area (radiation protection): YES
- To work in shift/rotation: YES
Technical:
- Working experience in Permit to Work Offices of nuclear power plants
Languages (Level):
- English (fluent)
- Ability with French, German or Finnish would be a plus.
The strong PTW team is in the PTW office beside the main control room.
Tasks of the team:
- Follow up of the 3 day’s program for all tasks on the site
- Release of all work orders
- Organization of the execution and normalization of blockings
- Organization of the execution of periodic tests
- Supervision of the plant status in relation on needed and available systems
- Online trouble shooting – solving of conflicts between different tasks
- Inform the main control room about all activities
Normal Tasks:
- Technical clarification of work orders / Permits to test and creation and validation of blockings / simulations.
- Planning of works / tests from work order creation, via blocking creation, work execution up to finalization of works/tests
- Management of the interfaces of the different departments for all kind of works
- Release of all work orders
- Organization of the execution and normalization of blockings
Expected Deliverables:
- Validated work orders and blockings
- Carried out blockings
- Work programs
Interfaces with:
- Shift supervisor and other shift team members
- OIO manager
- Plant status management
- PTW Office manager
- Other PTW Officers
- Commissioning Engineers
- Client